The Australian Renewable Energy Agency (ARENA) announced yesterday it would be providing $5.5 million support for an off-grid hybrid power project on Flinders Island.

Flinders Island is situated 54 kilometres from Cape Portland on the north-eastern tip of Tasmania and is the largest island in the Furneaux Group. Like many island communities, it relies heavily on polluting, expensive diesel fuel for power generation that must be shipped in.

That’s about to change.

The Hydro Tasmania project will utilise a combination of solar power, wind energy, diesel generation, flywheel and battery energy storage; plus associated technologies. It’s expected the project will reduce the island’s diesel consumption by more than 60%.

“The Flinders Island project will build on the success of a similar project Hydro Tasmania developed on King Island with ARENA support, which is delivering 100 per cent renewable energy to the island when conditions allow,” said ARENA CEO Ivor Frischknech.

A novel aspect of the Flinders Island project will be the development of a series of modular units fabricated off-site to create a portable hybrid energy solution.

With Australia home to many off-grid communities and industries, what is learned through Flinders Island will be shared nationally to promote competitive, reliable renewable energy power solutions and help reduce reliance on diesel fuel for electricity generation. The equipment developed could also serve temporary uses such as in disaster relief or in the mining industry.

“This low-cost, scalable approach has the potential to be a real game changer in remote areas – reducing the amount of construction and engineering work needed to be carried out on site would significantly reduce costs, risks and construction time,” said Mr. Frischknech.

The $12.9 million Flinders Island project is scheduled for completion in November 2016.

In addition to a massive hydropower portfolio and the successful King Island Renewable Energy Integration Project (KIREIP), Hydro Tasmania operates some of Australia’s largest wind farms, including the Musselroe (168MW), Bluff Point (65MW) and Studland Bay (75MW) facilities.

Hydro Tasmania’s wind farms harness the energy of the “Roaring 40’s” – strong westerly winds found in the Southern Hemisphere, generally between the latitudes of 40 and 50 degrees.

ARENA was established by the Australian Government on 1 July 2012 with a mission to invest in research and development of renewable energy projects and technologies. ARENA was in the crosshairs of the Abbott government last year, but survived and  is currently supporting more than 200 projects.

Energy Matters has been Australia’s trusted source of renewable energy news and education since 2005. We offer free services: providing free solar quotes, free battery quotes, and connecting home and business owners with local and pre-vetted installers.

“Energy Matters believes in a clean energy future. Australia’s road to electrification will be paved with solar, battery, and other renewable energy tech adoption – from households to industry. Our goal is to see Australia move towards net-zero” – Roshan Ramnarain, CEO of Energy Matters

Find out more information about solar across Australia:
Solar Panels Brisbane, Solar Panels Melbourne, Solar Panels Sydney, Best Solar Panels Canberra, Reputable Solar Companies Perth, Solar Panels Darwin, Solar Panels Hobart, and Solar Panels Adelaide.

Footer subscribe

By submitting your contact details provided on this form you are giving consent for one of our Solar Partners to contact you by Phone, Email, or SMS for a period of 90 days to discuss the solar-related products you have enquired about today. Your consent can be revoked at any time by either verbal or written confirmation.